Thacker Pass lithium project cost surges $900 million to $3.83 billion as construction advances

By: ICN Bureau

Last updated : November 16, 2026 4:09 pm



The revised estimate represents a 31% increase from the company's previous $2.93 billion projection


Lithium Americas has raised the estimated cost of building its flagship Thacker Pass lithium project in Nevada by nearly $900 million, taking the Phase 1 price tag to $3.83 billion, even as construction advances towards a targeted late-2027 mechanical completion and commercial production in 2028.
 
The revised estimate represents a 31% increase from the company's previous $2.93 billion projection. The company attributed the escalation to higher labour costs, mounting installation expenses, inflation in contractor wages, tariffs and logistics challenges.
 
Despite the substantial cost increase, Lithium Americas said the additional funding requirement is expected to be covered through company contributions and funds available in reserve accounts under its US Department of Energy (DOE) loan arrangements.
 
The company estimates that the project will require an additional $995 million in funding, including $895 million in incremental capital expenditure, $58 million in additional sustaining capital reserve requirements and $42 million in other net funding adjustments.
 
Under agreements involving the DOE and General Motors (GM), the funding gap is expected to be met through $650 million in contributions from Lithium Americas to the project joint venture and $315 million drawn, as required, from existing DOE loan reserve accounts.
 
The company said the revised funding arrangements will also increase its ownership percentage in the joint venture.
 
Labour-related expenses account for a substantial share of the cost escalation.
 
Lithium Americas estimates that higher craft labour wage rates and compensation packages have added approximately $150 million to the project cost. Another $245 million increase stems from higher-than-anticipated labour hours required to install piping, structural steel and equipment.
 
The company attributed the pressure to intense regional competition for skilled union workers and limited availability of experienced construction personnel.
 
Additional increases include approximately $100 million in engineering, procurement and construction management costs, $150 million in contractor and engineering staff wage inflation, and $150 million in additional contingency provisions.
 
Tariffs and logistics have contributed another $100 million.
 
The company said the tariff exposure estimate has fallen to approximately $60 million from an earlier estimate of $80 million to $100 million, as most equipment and materials have now been received.
 
However, higher fuel prices, shipping disruptions, limited US fabrication capacity and the need to reroute shipments have pushed up logistics expenses.
 
Despite the cost pressures, construction activity at Thacker Pass is advancing, with the company reporting significant progress in engineering, procurement and site installation.
 
As of September 30, 2026, approximately 1,900 personnel were working at the project, including more than 1,600 craft workers. The workforce is expected to increase to around 2,200 by the end of 2026 as construction reaches peak activity.
 
The project has recorded 4.7 million work hours without a serious injury or lost-time incident.
 
Detailed engineering has been completed, while procurement is more than 90% complete. More than 80% of the value of third-party contracts has been committed, with over 50% of that value already incurred.
 
Around 60 truckloads of equipment and materials were arriving at the site daily near the end of September, including major equipment such as the 115 kV main transformer, steam turbine generator and large process vessels.
 
All major structural steel had been delivered by the end of August, while installation work across key processing facilities continues.
 
Piping installation is also progressing, with 80% of the required fabricated piping material either delivered to the site or in transit by the end of October.
 
Lithium Americas is targeting completion of major structural work, delivery of remaining packaged equipment, completion of concrete foundations and the start of early utility commissioning before the end of 2026.
 
Once fully operational, Phase 1 of Thacker Pass is designed to produce approximately 40,000 tonnes of battery-quality lithium carbonate annually.
 
The project is considered a strategically important component of efforts to establish a domestic US lithium supply chain and reduce dependence on imported battery materials.
 
Jonathan Evans, President and Chief Executive Officer of Lithium Americas, said, "Thacker Pass is on track to deliver America's largest fully integrated source of domestic battery-quality lithium carbonate, and we are building it at pace. Phase 1 is advancing toward peak construction activity by year end 2026, with mechanical completion targeted for late 2027. 
 
"Despite external and internal factors impacting the Project’s capital cost estimate, the anticipated capital cost for Thacker Pass are expected to remain funded as we continue to deliver on our execution plan and bring the Project safely into production. As construction advances to piping and electrical installation, we are building our Operations and Business Readiness team to support the transition from developer to operator."
 
He added, "Lithium is a strategic asset, and Thacker Pass is the nation's clearest near-term path to a reliable domestic supply. As one of the largest construction projects in Nevada, the Project is already putting nearly 2,000 skilled craftspeople to work in Humboldt County, and that number is still growing. 
 
"This Project will help anchor the supply chains driving American economic competitiveness and support growing demand from the lithium-ion battery markets for electric vehicles and energy stationary storage. Thacker Pass is essential to America's economic and national security, and we are committed to delivering it."
 
Lithium Americas has increased its 2026 capital expenditure guidance to between $1.7 billion and $2 billion, up from the earlier range of $1.3 billion to $1.6 billion.
 
The company expects spending to peak this year, with the remaining expenditure spread across 2027 and into 2028 during the project's ramp-up period.
 
As of September 30, 2026, cumulative capital expenditure on Thacker Pass Phase 1 construction stood at approximately $2.26 billion. Total cumulative capital spending, including other development costs and capitalised interest, reached approximately $2.45 billion.
 
The company reported approximately $1.3 billion in cash and restricted cash as of September 30, including $359.5 million held at the joint venture level.
 
It has also received $1.448 billion in cumulative advances under its DOE loan, including a fourth advance of $239 million in August 2026.
 
Construction is also continuing at the company's Transload Terminal west of Winnemucca, Nevada, which is expected to become a critical logistics hub for transporting reagents needed for Thacker Pass operations.
 
Rail stabilisation and sub-ballast installation had reached 95% completion in the third quarter of 2026. The first concrete has been poured, powerline relocation has begun and construction of the main-line railroad turnout has been completed.
 
Completion of the terminal is targeted for 2027, in line with the planned startup of Thacker Pass.
 
Evans said the company remains focused on maintaining the construction schedule despite the higher cost estimate.
 
"I am proud of the construction progress we have achieved to date and the focus and hard work in completing the definitive capital cost estimate while also maintaining our target of mechanical completion in late 2027. Our Board and everyone across Lithium Americas, including Bechtel, are focused on bringing Thacker Pass to full commercial production in 2028."
 
Thacker Pass is owned by a joint venture between Lithium Americas and General Motors, with the US Department of Energy also playing a significant financing role.
 
The project's revised cost estimate underscores the financial and execution challenges involved in building a large-scale domestic lithium supply chain in the United States.
 
While advanced engineering and procurement, completed earthworks and the arrival of key equipment have reduced several construction risks, Lithium Americas acknowledged that attracting and retaining skilled workers and maintaining planned installation rates remain major challenges.
 
The company is now working with the DOE and GM to finalise the implications of the revised funding arrangements on ownership interests in the joint venture.
 
For Lithium Americas, the immediate challenge is clear: contain further cost escalation, maintain construction momentum and deliver Thacker Pass on schedule.
 
If successful, the project will provide a significant new source of domestically produced battery-grade lithium for the US electric vehicle and energy storage industries. But with the price tag now approaching $4 billion, execution will be under intense scrutiny.

Lithium Americas Thacker Pass lithium project General Motors US Department of Energy