Eni secures Indonesia’s approval for $8 trillion-cubic-feet gas development

By: ICN Bureau

Last updated : November 24, 2026 10:13 am



Once operational, the Geliga-Gula production hub is expected to reach peak output of 1 billion cubic feet of gas per day


Eni has secured Indonesian government approval for the development of the giant Geliga gas field, clearing a major hurdle for an ambitious project that will unlock an estimated 8 trillion cubic feet (Tcf) of gas resources in the Kutei Basin.
 
The approval of the Plan of Development (POD) for Geliga, located in the Ganal Production Sharing Contract (PSC), comes just six months after the discovery and marks a significant step forward in Eni’s plans to expand its gas production footprint in Indonesia.
 
The development will integrate the newly discovered Geliga field with the existing Gula discovery, bringing their combined estimated gas in place to approximately 8 Tcf. The project also includes 250 million barrels of associated condensate from Geliga.
 
Once operational, the Geliga-Gula production hub is expected to reach peak output of 1 billion cubic feet of gas per day (Bcf/d) and 50,000 barrels of condensate per day.
 
The project will establish a third major production hub in the Kutei Basin, complementing the existing South Hub and the North Hub, which is currently under development following a final investment decision (FID) announced earlier this year.
 
Together, the three hubs are expected to propel Eni's gross production in East Kalimantan to approximately 3 Bcf/d of gas and 140,000 barrels of condensate per day by the end of the decade.
 
The production will supply both domestic and international markets, supported by synergies with existing infrastructure, including the Bontang liquefied natural gas (LNG) plant and the Jangkrik Floating Production Unit (FPU).
 
The Geliga-Gula development will involve the installation of 15 subsea wells, associated flowlines and a newly built Floating Production, Storage and Offloading (FPSO) vessel.
 
The FPSO will have processing capacity of approximately 1 Bcf/d of gas and 80,000 barrels of condensate per day, alongside storage capacity of 1.4 million barrels.
 
Gas will be processed onboard the FPSO and transported through pipelines to the onshore receiving facilities at the Santan Terminal and into East Kalimantan's gas network.
 
A portion of the gas will be liquefied at the Bontang LNG facility, while the remainder will be directed to Indonesia's domestic market through the pipeline network.
 
Condensate will be stabilized and stored onboard the FPSO before being transferred to shuttle tankers for transportation.
 
The Geliga project is expected to benefit from significant operational and infrastructure synergies with the North Hub development, which is scheduled to begin production in 2028.
 
The integration is expected to help optimize project costs and execution timelines.
 
The development also forms part of a broader wave of upstream investments in Indonesia, alongside the ongoing North Hub and Gendalo-Gandang projects. Eni said these initiatives stem from its strategic partnership with SKK Migas and are expected to boost local content, increase utilization of available capacity at the Bontang LNG plant and strengthen gas supplies to the domestic market.
 
The approval also marks another milestone in the development of Eni's legacy assets in the Kutei Basin. The Geliga field is now operated by Searah, the independent upstream energy company established through the strategic partnership between Eni and PETRONAS.
 
Eni directly operates the Peri-Mahakam PSC, the Makassar Strait PSC and the recently awarded Sapukala Block.
 
In October 2026, the company also signed two binding agreements to sell interests in selected Indonesian upstream assets operated by Searah to Pertamina and Medco.
 
Established in June 2026, Searah is jointly owned by Eni and PETRONAS, with each company holding a 50% stake. The venture combines the two companies' portfolios, technical capabilities and regional expertise to develop upstream opportunities across Indonesia and Malaysia.
 
Searah's portfolio comprises 19 producing and development assets, including 14 in Indonesia and five in Malaysia. The company currently produces approximately 350,000 barrels of oil equivalent per day (kboe/d) and aims to exceed 500,000 boe/d of sustainable production by 2028.
 
The rapid approval of Geliga, following its discovery just six months earlier, underscores the pace of Eni's development strategy in Indonesia and the growing importance of the Kutei Basin in meeting regional and international gas demand.

Eni gas development