Aarti's installed production capacity for ethylation has increased from about 8-10 KTPA to about 25-30 KTPA
Aarti Industries Ltd has completed its project works in respect of its project capacity enhancement of ethylation unit at Dahej SEZ Unit in the Gujarat.
The company has successfully commenced the production at this expanded facility. With this expansion the company's installed production capacity for ethylation has increased from about 8-10 KTPA to about 25-30 KTPA.
This expansion also provides the flexibility to the company to multipurpose its overall ethylation capacity for various ethylation and propylation products as well as scale up the volumes in respect of its nitro-toluene chain products.
Subscribe To Our Newsletter & Stay Updated