The company is planning a mega expansion plan with respect to chemicals such as Caustic Soda, Chloromethanes, Phosphoric Acid, Hydrazine Hydrate and Chlorotoluene.

  • By Pravin Prashant | August 30, 2020
The Gujarat Alkalies and Chemicals Limited (GACL) is planning a mega expansion plan with respect to chemicals such as Caustic Soda, Chloromethanes, Phosphoric Acid, Hydrazine Hydrate and Chlorotoluene. 
 
The company has already planned a Caustic Soda Plant with Coal Based Power Plant in a Joint Venture with NALCO (GACL - 60% and NALCO - 40%). The cost of the plant is Rs. 2,000 crore and as per status - Caustic Soda is 87% complete whereas Power Plant is 72% complete. Another Caustic Soda Expansion at Dahej and Coal Based Power Plant has a capacity of 525 TPD and 65 MW is 12% complete and will cost Rs. 875 crore. 
 
Expansion Projects at Gujarat Alkalies and Chemicals Limited (GACL) 
1. Caustic Soda New Plant with Coal Based Power Plant (JV with NALCO) 
Capacity - 800 TPD + 130 MW
Cost - Rs. 2,000 crore 
Progress Status* - CS Plant - 87%, Power Plant - 72% (Including Common Infrastructure ) 
 
2. Chloromethanes Plant at Dahej 
Capacity - 300 TPD 
Cost - Rs. 800 crore 
Progress Status* - 66% 
 
3. Phosphoric Acid (New) 
Capacity - 100 TPD 
Cost - Rs. 390 crore 
Progress Status* - 12%
 
4. Hydrazine Hydrate 
Capacity - 30 TPD 
Cost - Rs. 405.50 Cr 
Progress Status* - 50%
 
5. Chlorotoluene Plant at Dahej
Capacity - 120 TPD 
Cost - Rs. 120 Cr
Progress Status* - To be Implemented 
 
6. Caustic Soda Expansion at Dahej and Coal Based Power Plant
Capacity - 525 TPD and 65 MW 
Cost - Rs. 875 Cr 
Progress Status* - 12%
 
Source: Indian Chemical News 
* As on 25.07.2020 
 
The Chloromethanes plant at Dahej cost Rs. 800 crore and is 66% complete. The plant has a capacity of 300 TPD. The Phosphoric Acid Plant capacity is 100 TPD and is 12% complete. The Hydrazine Hydrate Plant has a capacity of 30 TPD and is 50% complete. The Chlorotoluene Plant at Dahej is yet to be implemented. The plant will cost Rs. 120 crore and will have a capacity of 120 TPD.  
 

Register Now to Attend Chem Connect 2025 on August 21th 2025, Novotel Mumbai International Airport

Upcoming Conferences

Chem Connect 2025

August 21, 2025

Other Related stories

Startups

Petrochemical

Energy

Digitization