GSFC announces forced safe shutdown of Urea II plant
General

GSFC announces forced safe shutdown of Urea II plant

The leakage in bottom thermo well of Urea Reactor (XUR-101) was noticed on July 16.

  • By ICN Bureau | July 18, 2022

Gujarat State Fertilizers & Chemicals Limited has announced the forced safe shutdown of Urea - II Plant. The plant was operating normal at 105% with Titanium MOC lined high pressure Urea Reactor (XUR-101) in service.

On 16th July 2022 night shift, the leakage in bottom thermo well of Urea Reactor (XUR-101) was noticed. The required actions of safe plant shut down were immediately taken.

The estimated time required to prepare standby Urea Reactor (XUR-102) for lining up after following all statutory checks will be Twelve (12) days subject to timely availability and passing through qualification test of the special Welder.

Considering shutdown and start up sequence, total Thirteen (13) days of production loss (Around 10400 MT of Neem Urea) is envisaged. However, Urea-l plant will continue to produce 320 MTPD production during this period.

Register Now to Attend Gujarat Chem & Petchem Conference 2025 on May 8-9th 2025, at Hyatt Place, Bharuch

Register Now to Attend NextGen Chemicals & Petrochemicals Summit 2025 on June 18-19th 2025, The Leela Mumbai

Other Related stories

Startups

Chemical

Petrochemical

Energy

Digitization