SRF commissions P38 manufacturing facility at Dahej
Chemical

SRF commissions P38 manufacturing facility at Dahej

SRF Board earlier approved a project to set up a dedicated facility to produce 300 MTPA of P38 at Dahej at an estimated cost of Rs. 61 crore.

  • By ICN Bureau | September 30, 2022

SRF Limited has informed that P38 manufacturing facility at Dahej has been commissioned and capitalized on 29th September, 2022 at an aggregate cost of Rs. 58 crore.

On 25th January, 2022 SRF Board had approved a project to set up a dedicated facility to produce 300 MTPA of P38 at Dahej at an estimated cost of Rs. 61 crore.