ECI Group has successfully started up and brought its first high-pressure polyethylene (HPPE) production line using its proprietary autoclave technology into operation, marking a significant milestone in the company's global technology expansion.
 
The new facility, developed at Jiangsu Hongjing (Sailboat)'s integrated refining and petrochemical complex in Jiangsu Province, China, has an annual production capacity of 100,000 tonnes of ethylene vinyl acetate (EVA).
 
The plant is part of Shenghong Holding Group, an international industrial conglomerate with interests spanning petrochemical refining, new energy, new materials and high-end textiles.
 
The successful start-up represents the first commercial-scale demonstration of ECI Group's proprietary autoclave technology in a greenfield HPPE production line.
 
“This is a major milestone for ECI Group,” said Joaquin Flores, President and CEO of ECI Group. “The successful start‑up of our first greenfield HPPE line validates the strength, flexibility, and reliability of our technology at full industrial scale. We are proud to support our valued client Sailboat in achieving safe and successful operations.”
 
The project has taken more than four years to move from licensing to commercial operation. ECI Group signed the technology licensing agreement with Sailboat in June 2022, with construction beginning in November 2023.
 
ECI Group supplied the licensed technology, complete engineering design, operator training and on-site technical support throughout commissioning and start-up. The project was delivered through close collaboration between the engineering, operations and commissioning teams of both companies.
 
Confirming the successful commissioning, the client said the unit achieved its first start-up and completed a successful single-run operation on September 22, 2026, producing products that met the required specifications.
 
“The Polymer division's HEV unit at Shenghong Petrochemical Industry Group implemented the ECI Group Autoclave process technology, successfully achieving its first startup and a successful single-run operation on September 22, 2026, producing qualified products. The advanced and simple process design of ECI Group, the efficient and stable control scheme, and the professional technical service team provided strong support for the smooth commissioning of this unit.”
 
Tony Wang, ECI China General Manager, said the company would continue supporting Sailboat throughout the facility's operating life, drawing on its local Chinese team and global polyolefins expertise.
 
“We look forward to continuing to partner with Sailboat through the lifecycle of the plant. With our dedicated team in China acting as the local focal point for ECI Group’s global polyolefins expertise, our goal is to support Sailboat, as well as the full range of polyolefin plant operators across China, to maximize reliability, performance, and long-term value from their operating plants.”
 
Chris Alayan, Project Director, highlighted the collective effort behind the project's delivery, from initial concept through construction and commissioning.
 
“Bringing this plant from concept to successful operation was a tremendous team effort. I would like to thank our project team for their hard work, ensuring the facility was designed, constructed, commissioned and started up safely and successfully.”
 
ECI Group said its technology was selected for the project because of its broad product capabilities, lower operating costs and forward-looking design, which allows for future capacity expansion and further product development.
 
The plant's production flexibility is expected to open access to multiple high-value market segments, with the ability to manufacture a wide range of homopolymer and copolymer grades.
 
“This project demonstrates the versatility of ECI Group’s HPPE technology platform,” said Chris Brock, Director of HPPE Technology at ECI Group. “With the wide range of homopolymer and copolymer grades the line is capable to produce, Sailboat can serve multiple high value market segments. We are proud to see this plant successfully start-up, demonstrating the strength of our technology and establishing a strong foundation for future HPPE projects worldwide.”
 
Technology partner Repsol also played a key role in the project, contributing technical expertise in copolymer production and plant operations, alongside know-how in developing differentiated applications. Its technical personnel supported design and safety reviews, training, commissioning and start-up.
 
Products from the new facility will supply a diverse range of downstream industries, including flexible and protective packaging, adhesives, footwear, wire and cable insulation, photovoltaic encapsulants, extrusion coatings and other specialty and industrial applications.
 
The plant has also been designed to accommodate the future production of additional high-pressure copolymers, giving Sailboat the flexibility to respond to changing market requirements.