100 Gati Shakti Cargo Terminal to be developed till 2025
Supply Chain

100 Gati Shakti Cargo Terminal to be developed till 2025

22 GCTs have already been commissioned whereas 125 applications for development of cargo terminals under the GCT Policy have been received and 79 in-principle approvals have been granted

  • By ICN Bureau | December 08, 2022

Under the Gati Shakti Cargo Terminal (GCT) Policy, it has been targeted to develop 100 GCTs in three years i.e. 2022-23, 2023-24 & 2024-25 says Minister of Railways, Communications and Electronic & Information Technology, Ashwini Vaishnaw in a written reply to a question in Lok Sabha. 

22 GCTs have already been commissioned whereas 125 applications for development of cargo terminals under the GCT Policy have been received and 79 in-principle approvals have been granted.

For GCTs to be developed on non-Railway land, the GCT operators will identify the location and will construct the terminal after obtaining necessary approval. For GCTs to be developed either fully or partially on Railway land, the land parcels will be identified by Railways, and the GCT Operator for construction and operation of the terminal will be selected through open tendering process.

Register Now to Attend Gujarat Chem & Petchem Conference 2025 on May 8-9th 2025, at Hyatt Place, Bharuch

Register Now to Attend NextGen Chemicals & Petrochemicals Summit 2025 on June 18-19th 2025, The Leela Mumbai

Other Related stories

Startups

Chemical

Petrochemical

Energy

Digitization