Contract awarded by Bechtel for MRCs includes three liquefaction trains, for a total of six Frame 7 gas turbines and 18 centrifugal compressors
Baker Hughes, an energy technology company, announced that it has been awarded an order by Bechtel Energy to supply three Main Refrigerant Compressors (MRCs) for NextDecade’s Rio Grande LNG project in the Port of Brownsville, Texas.
In total, Baker Hughes will supply six Frame 7 gas turbines paired with 18 centrifugal compressors across Rio Grande’s first three LNG trains in a parallel configuration arrangement, providing more operational flexibility – for a nameplate capacity of 17.61 MTPA.
“This order builds on our longstanding relationship with Bechtel and is a significant milestone in our partnership with NextDecade, supporting them on this key LNG project,” said Ganesh Ramaswamy, executive vice president of Industrial & Energy Technology at Baker Hughes. “We are delighted that our proven and reliable technology solution will support the production of LNG in the U.S., which is crucial in balancing energy affordability, security and sustainability globally.”
The Baker Hughes gas technology solution chosen for Rio Grande LNG provides NextDecade with the highest production levels for the plant’s design, as well as operational flexibility and high availability. The Frame 7 gas turbine is well-proven for its energy efficiency, availability, reliability and maintainability.
Packaging of the turbine/compressor train, a unique Baker Hughes offering, as well as assembly of the compressors and testing of the trains, will take place at Baker Hughes’ facilities in Italy.